Managing Scope Changes in TDX

Summary

A guide on how to manage Scope changes in TDX.

Body

This article explains how to manage scope changes using formal Change Requests in TDX.

Overview

What Is Scope Creep

Scope creep occurs when project requirements expand beyond the original agreement.

Example:
Adding additional rooms to a projector initiative without increasing the budget.

Procedures

Process for Submitting a Change Request

  1. Navigate to the project
  2. Select Actions
  3. Submit a formal Change Request
  4. Document:
    • Impact on timeline
    • Impact on budget
  5. Obtain approval from:
    • Project Manager
    • Client or Sponsor

Do not simply add new tasks without formal documentation.