Body

This article explains the two project management approaches available in TeamDynamix (TDX): Waterfall and Agile. It is intended to help departments understand the differences between the two options and select the approach that best fits their type of work.

The goal is not to require departments to become project management experts, but to provide enough context to make an informed and practical choice when setting up a project in TDX.

Table of Contents

Overview

Overview

When a project is created in TDX, departments are asked to select a project management approach. This choice affects how work is planned, tracked, and displayed throughout the life of the project. TDX supports both Waterfall and Agile approaches. Each approach is valid, and neither is considered better by default. The most appropriate option depends on the nature of the work being performed.

Uploaded Image (Thumbnail)

(You will be prompted to select either Card Wall or Waterfall when developing your initial plan for the project. In this specific case, the Card Wall is an agile feature. This is where the user’s decision will be solidified)

Waterfall Project Management

Waterfall is a traditional project management approach where work is planned in advance and completed in defined phases. Each phase is typically completed before the next phase begins.

Common phases may include:

  • Planning
  • Design
  • Execution
  • Review
  • Completion

In a Waterfall project, the overall scope and timeline are generally established early and change infrequently.

How Waterfall Works in TDX

In TDX, a Waterfall project:

  • Uses tasks and milestones to track progress
  • Follows a more linear sequence of work
  • Is well suited for projects with clearly defined requirements

Progress is measured by completing tasks and moving through planned phases.

When Waterfall is a Good Fit

Waterfall is often appropriate when:

  • The project requirements are well understood from the start
  • The work follows a predictable sequence
  • Changes are expected to be minimal
  • Formal approvals or compliance steps are required

Examples include policy development, system upgrades with fixed scope, or facilities-related projects.

Agile Project Management

Agile is an iterative approach to project management that focuses on completing work in smaller segments over short periods of time. Rather than planning all work upfront, Agile allows teams to adjust priorities as the project progresses.

In TDX, Agile work is commonly managed using Sprints and the Cardwall.

How Agile Works in TDX

In TDX, an Agile project:

  • Organizes work into short time periods called Sprints
  • Uses cards to represent individual work items
  • Tracks progress visually on the Cardwall
  • Supports ongoing adjustments as work evolves

Agile emphasizes visibility, collaboration, and incremental progress rather than strict phase-based planning.

When Agile is a Good Fit

Agile is often appropriate when:

  • The work is exploratory or evolving
  • Requirements may change over time
  • Progress is best tracked in smaller pieces
  • Ongoing collaboration is needed

Examples include process improvement initiatives, application development, and cross-functional projects with changing needs.

Key Differences Between Waterfall and Agile

Project Area

Waterfall

Agile

Planning style

Detailed planning upfront

Planning occurs continuously

Structure

Linear and phase-based

Iterative and flexible

Change management

Changes are limited

Changes are expected

Progress tracking

Tasks and milestones

Cards, Cardwall, and Sprints

Recommendation for Departments

The PMO Office recommends all Projects initially create a "Waterfall" plan to establish high level project deliverables, checkpoints, and validations. Then, if a Project is more suitable for Agile, a separate Cardwall plan can be created which provides the specific team tasks required to support key deliverables outlined in the Waterfall Plan.  

 If the Project requires a full Waterfall Plan due to its attributes described above, then this Project Plan will be filled in with more detail to support the process.  

Agile in TDX:

  • Works well with the Cardwall
  • Makes progress visible without complex planning
  • Allows departments to start small and adjust over time
  • Reduces the need for detailed upfront documentation

That said, Waterfall remains a strong choice for projects that are highly structured, time-bound, or governed by fixed requirements.

Departments should choose the approach that best aligns with how their work is actually performed, rather than trying to adapt their work to fit a specific methodology.

Additional Support

  • OU Technology Center
  • 44 Oakland Center
  • Rochester, MI 48309-4479
  • (248) 370-4357
  • Office Hours: M-F 8:00am - 5:00pm

Details

Details

Article ID: 1055
Created
Fri 7/17/26 9:55 AM
Modified
Thu 8/13/26 12:40 PM